Upgrading works for El-Moshir Tantawy Axis, from El-Wafaa & El-Amal Axis to the Ring Road, 4.1 km long
Scope of Work
- Milling and removal of failed/collapsed pavement areas.
- Construction of a 25 cm thick stabilized base layer (FDR).
- Construction of a 20 cm thick stabilized base layer (FDR).
- Supply and spreading of a 6 cm thick asphalt concrete binder layer after compaction.
- Supply and spreading of a 5 cm thick asphalt concrete surface layer.
- Supply and spreading of thermal geogrid mesh for cracks.
- Milling
Client
General Authority for Roads and Bridges
Duration
6 months
Execution Status
Completed