Upgrading the main runway, constructing a stormwater drainage system, and establishing an aircraft arresting barrier system for military aircraft at Aswan International Airport

Scope of Work
  • Construction of a cold-laid layer using the CIR technique on the main runway body and at intersection areas.
  • Construction of a stabilized base layer using the FDR technique in the pavement sections.
  • Resurfacing the main runway body and turning areas with asphalt pavement (binder + surface layers).
  • Applying a 2-meter-wide surface treatment and protective layer to strengthen the runway surface.
  • Re-marking and repainting the navigational signs on the main runway and connecting taxiways.
  • Constructing a new turn pad area.
  • Installing a polyester mesh in defective areas to connect new and old asphalt.
  • Constructing chambers for military aircraft arresting barriers on the main runway in both directions.

Client

Egyptian Airports Company

Duration

13 months

Execution Status

Completed