Upgrading of Main Runway 04R/22L, Maintenance of Taxiway A and Connectors, and Construction of Infrastructure and Rainwater Drainage System at Sharm El Sheikh International Airport

Scope of Work
  • Construction of a 30 cm stabilized base course at the first and last 400 m of the runway, and 5 m wide shoulders along both sides
  • Construction of a 45 cm base course in layers not exceeding 15 cm each
  • Construction of a 7 cm binder course along the main runway body
  • Asphalt resurfacing of the main runway body, new shoulders, and turn pads with a 6 cm surface course
  • Application of a surface treatment/protection layer for strengthening the entire runway and connectors
  • Milling with a uniform depth of 5 cm
  • Laying a 7 cm binder course in the required areas
  • Crack treatment after milling works
  • Installation of polyester geogrid in defective zones
  • Construction of concrete culverts beneath the runway, including inspection chambers
  • Re-marking and painting of aviation markings for Taxiway Alpha and connectors
  • Application of a strengthening/protection surface layer for Taxiway Alpha
  • Milling works for the connectors between the runways
  • Installation of polyester geogrid
  • Asphalt resurfacing of all milled areas
  • Re-marking and painting of airfield markings for Taxiway Alpha and connectors
  • Application of a surface strengthening/protection layer for the entire Taxiway area
  • Construction of concrete culverts beneath the connectors between the runways
  • Construction of a complete stormwater drainage system
  • Construction and implementation of an open channel with a grating cover.

Client

Egyptian Airports Company

Duration

18 months

Execution Status

Completed – Phase Two Ongoing